ePrivacy and GPDR Cookie Consent management by TermsFeed Privacy Policy and Consent Generator

Toulouse metro

Construction of package 4 of metro line C

Underground Works

France, 2023-2027

General description

In the context of an ambitious project to develop the city's transport infrastructure, the SMTCAT (Greater Toulouse joint association for public transport) has awarded Bouygues Travaux Publics the contract for section 4 of line C, which will be the city’s third line. With a 27-kilometre route and 21 stations, it will link the north-west and south-east areas of the city, serving the region's major employment centres. The new line will be able to handle 200,000 passengers a day.

The contract awarded to Bouygues Travaux Publics includes:

- A 4,160 metre-long tunnel bored with a tunnel boring machine, with an internal diameter of 8.50 metres

- 4 stations: Montaudran Gare, L’Ormeau, Limayrac-Cité de l’Espace and Côte Pavée

- 3 ancillary structures and the galleries connecting them to the tunnel

- A 650-metre-long cut-and-cover tunnel at the southern end of the section at Montaudran

Consortium

Horizon (Bouygues Travaux Publics, Bouygues Travaux Publics Régions France, Soletanche Bachy, Soletanche Bachy Tunnels, Bessac)

Project owner

Tisséo Ingénierie

Locations