General description

Construction of a barrage on the Seine for regulating the level of the upstream reach between the Suresnes and Chatou/Bougival river barrages. It is immediately upstream of the existing barrage which was demolished when the new structure was handed over. Project carried out as part of a consortium.

MAIN CHARACTERISTICS

Barrage equipment:

- Three main 30.50-m-wide sluices, each fitted with a bottom-hinge gate operated by two hydraulic cylinders, and a fishway at the left-bank end of the structure (Chatou Island side)

- A steel footbridge crossing the new barrage and connecting the right bank to the island where the new barrage control building is sited. 

Equipment upstream:

- Construction of a bulkhead-gate storage area (island side)

- Extension of training wall to upstream tip of island

- Cable laying by boat.

Consortium

BOUYGUES TRAVAUX PUBLICS REGIONS FRANCE / TRAVAUX PUBLICS REGIONS PARISIENNE

Project owner

VOIES NAVIGABLES DE FRANCE

Key figures

1

works programme subject to river floods

3

sluices built

1

turnkey operation

Locations

Associated Projects

Caucedo container terminal
Caucedo container terminal

First cargo port on the island River and Maritime Works

More info
Pusan Port
Pusan Port

Design, construction, and supply of equipment - Concession

More info
Beirut Seafront
Beirut Seafront

Seafront promenade and marina

More info